When a storm moves through like the one we had Nov. 16–18, Wilton Manors residents hold their breath and grab their waders. The National Weather Service estimates the city got up to eight inches of rain from Tuesday night into Wednesday morning.
The city has spent millions of dollars over the past few years to shore up existing pipes and modernize facilities. While there were two spill locations (NE 5th Avenue and NE 21st Court; and NE 26th Street and North Andrews Avenue), City Manager Leigh Ann Henderson says the new equipment is starting to do the job.
“The volume of these spills was considerably lower than what we experienced during similar storm events before the city's investments in inflow and infiltration (I&I) reduction.”
The system, and city, caught a break on Wednesday when forecasts of additional inches of rain didn’t materialize.
Water and sewage rates, which are heavily influenced by Fort Lauderdale and its new plants and improvements, continue rising. Many Wilton Manors citizens feel they’re paying more while seeing the same issues repeat.
Infrastructure repairs and upgrades are expensive and often disruptive. They are never a simultaneous, citywide endeavor. Each section of pipe is its own project.
With that in mind, Henderson says the city will continue implementing its long-term plan.
“We continue to move forward with additional projects to further reduce I&I and strengthen the resilience of our sanitary sewer system.”